Saturday, June 22, 2013

Updates 6/22/2013

I posted a bunch of pics on the Construction tab -

We were excited to see that they finally moved the dirt pile from the back of the house - they will have a LOT of grading to do I'm sure - still concerned with drainage issues. Anyway......

We met with Guardian (they handle the cable, phone, data, and security for this area) and identified where we wanted all of our cables run; they came out yesterday and got it done!

Still no roof for our bay window or shower pan in the Master Bath but the good news is they were finishing our roof (finally) today when I was leaving.

I did notice replacement sashes for the broken windows in the garage ready to be put in and they cut out the sitting area windows to prepare for the double door (currently sitting in the Garage as well) to be placed.

Electrical, plumbing, HVAC, Cables done but electrical is going to have to come back out Monday and here's at least one reason why - we got the 4' extension and we got coffered ceiling in the Family room. When we identified with our SR where we wanted the can lights in the Family Room we did not place them on the same row as the fan (intentional) but when we see that there are can lights on the same row as the fan and it's off because we did the 4' ext in the Family Room and apparently when we were looking at the plan and marking the can lights we didn't know it was going to add another row for the coffered ceiling so it looks off. Our PM said the electricians are coming back on Monday and I HOPE it's to adjust this.

We have noticed our PM has gone through and identified a lot of things that need to be fixed with spray paint and it's great to see! We have our pre-drywall meeting scheduled Monday afternoon.